Key Action Dates
- Release RFO Date: October 29, 2012
- Questions Due Date: November 1, 2012 by noon
- Response to Questions Due Date: November 5, 2012 by 4PM
- Offers Due Date: December 7, 2012 by noon
- Notice of Intent to Award January 4, 2013
- Estimated Term Dates: February 1, 2013 through January 31, 2015
- County Board of Supervisors Approval Due Date: January 31, 2013 by 5PM
Covered California will respond to a portion of the
Counties’ questions and will post the answers on its website as scheduled by
4:00 pm on November 5th. The remaining questions will be addressed at the Bidders
Conference. The Bidders Conference will be scheduled for the week of November
5th. Detailed Information regarding the Bidders Conference will be posted to
the website by November 5th.
Covered California is considering amendment to the
RFO to further address the questions. Amendment may be reflected in an
Addendum.